Reko Diq costs reach USD 9.1Bn, ICMA flags financial risks
Research highlights 30% cost escalation and potential delays affecting Pakistan's USD 1.88 billion SOE investment commitments

Business Desk
The Business Desk tracks economic trends, market movements, and business developments, offering analysis of both local and global financial news.

Reko Diq's estimated capital costs have increased 30% to USD 9.1 billion from USD 7 billion, raising concerns over financial exposure and prospective returns for Pakistan's state-owned investors, according to research by the Institute of Cost and Management Accountants of Pakistan (ICMA).
How could Reko Diq's rising costs affect state-owned firms?
Three federal state-owned enterprises, OGDCL, PPL and GHPL, have collectively committed approximately USD 1.88 billion to the copper-gold project. ICMA warned that higher capital costs and potential production delays could increase financing exposure, postpone dividend income and raise the opportunity cost of committed capital, underscoring the importance of transparent oversight and investment accountability.
In its latest Economy Watch analysis, titled Creating New Economic Value: The Strategic Significance of Reko Diq for Pakistan's SOEs, ICMA examined the project's investment structure, financial exposure, economic potential and implications for state-owned enterprise (SOE) reform.
The analysis highlighted the increase in estimated project capital costs from USD 7 billion to USD 9.1 billion and warned that escalating costs could affect the prospective returns of public-sector investors.
Initial production could shift from the original end-2028 target to 2030, potentially delaying financial returns for the participating SOEs.
ICMA called for regular project monitoring, realistic investment assessments and transparent disclosure to manage these risks.
How much economic value could Reko Diq generate for Pakistan?
Reko Diq is projected to generate approximately USD 74 billion in free cash flow over its estimated 37-year mine life, with employment expected to reach 7,500 workers during peak construction and around 4,000 permanent jobs during operations.
However, ICMA cautioned that project-level free cash flow should not be treated as revenue accruing directly to Pakistan.
The country's economic benefits will depend on dividends, taxes, royalties, reinvestment and the extent of domestic participation in the project.
The research also warned that mineral wealth alone does not guarantee domestic industrial development.
Reko Diq's current design envisages producing copper-gold concentrate, with smelting and refining outside the project's existing scope.
ICMA recommended developing commercially viable local supply chains, strengthening technical skills and increasing Pakistani firms' participation in engineering, construction, transportation and maintenance.
It also called for exploring domestic mineral processing opportunities where infrastructure, energy supplies and market conditions make such investment commercially viable.
What reforms does ICMA recommend for public-sector investment?
ICMA said participation in strategic national assets should be supported by sound commercial decisions, clear shareholder accountability, independent oversight and measurable performance indicators.
The analysis emphasized that SOEs should develop into strategic investors rather than simply acquire ownership stakes in valuable assets.
The objective should be to ensure public investments generate sustainable financial returns alongside broader economic benefits.
The research linked Reko Diq's development to Pakistan's wider SOE reform agenda, emphasizing the need for cost discipline, transparent governance and stronger domestic economic participation.